In May–June 2014, we relocated production in the Pehamet Sp. z o.o. works. Project scope: Demolition of old foundations, Construction of new […]
July
10
2014
In May–June 2014, we relocated production in the Pehamet Sp. z o.o. works. Project scope: Demolition of old foundations, Construction of new […]
Thermal insulation of the dust collection system for WR-25 boiler no. 3 at ECO Opole
Supply and assembly of a steel structure (48 tonnes) Reinforced-concrete structures, including supply and installation of prefabricated pillars Installation of […]
Construction of roof of the boiler room and installation of room equipment, such as catwalks, platforms, railing, staircase, hoist beams