Soda Polska CIECH S.A.

A project carried out on the premises of Soda Polska CIECH SA – welding of structures and plates of reactor ductwork in a newly constructed SCR installation, using the MIG/MAG and MMA processes. A project carried out for Chemoservis-Dwory SA. Construction of a Selective Catalytic Reduction (SCR) installation – assembly of a steel structure and ductwork for the reactor of K1 and K4 boilers

Michelin Polska LTD

In February–May 2015, we disassembled 4 rubber production lines at lMichelin Polska Project tasks:

  • Disassembly of 4 mixer lines intended for reuse along with a system for rubber feeding and receipt, a total weight of about 500 tonnes
  • Securing the devices for the time of transport
  • Loading onto lorries
  • Disassembly of selected component devices and systems of the rubber production line to be scrapped. The entire scrapping process took place on site under conditions of an increased risk, using intrinsically safe techniques

About 250 tonnes of devices were disassembled for scrapping.

Chemar Armatura LTD

In June–September 2014, we relocated the works of Chemar Armatura Sp. z o.o. with their production continuity preserved.

Project scope:

  • Disassembly of 34 conventional and CNC machine tools,
  • Transport to a new location
  • Repeated assembly and commissioning
  • Production tests

The entire process took place during normal production and required of us perfect coordination of all tasks. Relocation was successful and completed in line with the adopted time schedule.

Pehamet Sp. z o.o.

In May–June 2014, we relocated production in the Pehamet Sp. z o.o. works.

Project scope:

  • Demolition of old foundations,
  • Construction of new foundations for the process line,
  • Disassembly, relocation and new commissioning of the packaging line for non-ferrous metal stripes,

The entire process took place during normal production and required of us perfect coordination of all tasks. Relocation was successful and completed in line with the adopted time schedule.

Plastic Omnium

Supply and assembly of a steel structure (48 tonnes)

Reinforced-concrete structures, including supply and installation of prefabricated pillars

Installation of an electric wiring system, including indoor and outdoor lighting

Construction of an access road for lorries

Plastic Omnium Auto Exteriors

We were assigned by Plastic Omnium Auto Exteriors to relocate a vacuum feeding system. As part of the project, we transported two silos (with a height of 13 m and diameter of 3 m each) from Germany do Poland and completed assembly tasks in Gliwice including:

  • Disassembly of feeding and control infrastructure
  • Construction of new systems for material receipt
  • Installation of a new control system
  • Installation of a new pneumatic system

ECO

ECO SA assigned us to install a dust collection system for the WR-25 boiler at their Combined Heat and Power plant in Opole.

The project included among others the following construction and mechanical works:

  • Designing and construction of foundations for industrial fans
  • Assembly of a steel structure with ancillary equipment (with a total weight of about 48 tonnes)
  • Design, supply and assembly of electrical wiring, instrumentation, control and automation systems
  • Construction of a dust collection system for the WR-25 boiler at the Combined Heat and Power plant in Opole

TAURON Ciepło

An on-site project at TAURON Ciepło Sp. z o.o., Tychy Generation Plant: disassembly of the old flue-gas ductwork with disposal of mineral wool, assembly of a new ductwork with platforms, expansion joints, shutter flap, thermal insulation along the new stretch. A project carried out for Bilfinger Elwo SA. Disassembly and assembly tasks as necessary to replace a flue-gas ductwork leading to the chimney with ductwork adaptation and thermal insulation